Fabrik Advisory was founded in 2026. The work below was co-led by Oliver David Krieg before then, at Intelligent City and at the University of Stuttgart. It is the experience every engagement draws on.

Industry

Intelligent City, Vancouver · 2018 to 2026

Aerial view of 230 Royal York Road during assembly
Photo: Intelligent City

Toronto, Ontario · 2026

Halsa 1 - 230 Royal York Road

Building
Nine-storey mass timber residential, 60 units
Scope
Prefabricated structure and envelope
Developer
Windmill and Leader Lane Developments
Role
President, Intelligent City

What it shows

A structural and envelope building system that fit together. The first full-scale delivery of prefabricated mass timber components for high-rise housing.

Chief Leonard George Building, street elevation
Photo: GBL Architects

Vancouver, British Columbia · 2025

Chief Leonard George Building

Building
Mass timber social housing, 79 units
Scope
Prefabricated Passive House facade
Developer
BC Indigenous Housing Society
Role
Chief Technology Officer, Intelligent City

What it shows

A fully integrated envelope system with windows, insulation, and cladding, to meet Passive House performance. The first project out of Intelligent City's pilot factory.

Robotic production line in the factory
Photo: Kristopher Grunert

Delta, British Columbia · 2020 to 2025

Automation in prefab pilot factory

Facility
Multiple robot cells, more than 25 production staff
Capacity
300 to 500 panels annual production
Role
Chief Technology Officer: planning, commissioning and ramp-up

What it shows

A factory is a business decision as much as an engineering one. Volume, product mix, material flow, and pipeline decide whether automation pays.

A finished facade panel with windows and cladding in the factory
Photo: Intelligent City

Vancouver · 2018 to 2026

Building platform and product strategy

Platform
Parametric software, DfMA and manufacturing automation in one building system
Strategy
Repositioned from turnkey provider to prefabricated component supplier
Growth
From 5 to 45 people; more than CA$30M in equity and grant capital
Role
Director of Technology, then CTO, then President

What it shows

A building platform is a product. It needs a roadmap, an architecture and a business model that developers and lenders can underwrite.

Research

ICD, University of Stuttgart · 2012 to 2018

BUGA Wood Pavilion, a segmented timber shell

Heilbronn, Germany · 2019

BUGA Wood Pavilion

A 30-metre segmented wood shell. A robotic platform assembled and milled its 376 bespoke hollow wood segments, which fit together with sub-millimetre precision.

Role: scientific development and management, in a team, through to the manufacturing phase in 2018. Photo: ICD/ITKE, University of Stuttgart

Interior of the Landesgartenschau Exhibition Hall, a timber plate shell

Schwäbisch Gmünd, Germany · 2014

Landesgartenschau Exhibition Hall

The first building with a primary structure made entirely of robotically prefabricated beech plywood plates, 50 mm thick. Computational design, simulation, fabrication and surveying worked as one process.

Role: scientific development, planning and fabrication, in a research team. Photo: ICD/ITKE, University of Stuttgart

Contact

Start with a conversation.

Tell us what you are trying to build. The first conversation is confidential and without obligation.

Email

Based in

Vancouver, British Columbia. Working across Canada.

Elsewhere

LinkedIn